Timeline

Van Ness Arial View
Campus at Van Ness & Geary – view looking southeast from Van Ness & Post

While development and changes are planned at each of California Pacific Medical Center's campuses, the cornerstones of our plan to Rebuild CPMC are: the new full-service community hospital at our St. Luke's Campus, and the new acute care and Women & Children's hospital at Van Ness & Geary. The following is an overview of the anticipated environmental review process and construction schedule.


Review Process

Environmental Review
Draft EIR (Environmental Impact Report): published July 21, 2010
Public Hearing on Draft EIR: September 23, 2010
EIR Certification & Approvals at the Board of Supervisors: October 2011-January 2012

Construction

Campus at Van Ness and Geary
New Hospital Construction: 2012-2016
Open for Patient Care: 2016
New Medical Office Building Construction: 2012-2016

St. Luke's Campus
New Hospital Construction: 2012-2016
Open for Patient Care: 2016
Future Expansion: Medical Office Building: 2016-2020

Pacific Campus
Move Acute Care services to Campus at Van Ness and Geary: 2016
Renovate Hospital to Ambulatory Care Center: 2016-2017*
New ACC Addition & Parking: 2017-2020*

Davies Campus
New Neurosciences Institute: 2012-2014
New Castro/14th St. Medical Office Building & Parking: 2018-2021*

California Campus
No Construction planned at this time
Move Acute Care services to Campus at Van Ness and Geary: 2016
Move Ambulatory services to Pacific Campus: 2016 - 2020

* Please note that plans marked with an asterisk are long-term projects. Project approvals are not being sought for long-term projects at this time.

California Pacific Medical Center
PO Box 7999
San Francisco, CA 94120

phone: 415-600-6000
email: cpmcadmin@sutterhealth.org
Your Privacy

Powered by ARCOS | Design by Plus Three
Copyright 2012 California Pacific Medical Center